The Oregon Department of Transportation completed repairs to OR 82 near Lostine that was damaged by December 2024 storms, the agency said. Rockfall barrier work finished in September and culvert repairs wrapped up in late October, according to ODOT.
Heavy rain in December 2024 triggered a rockfall at milepost 57, sending rocks and debris onto the highway and leaving the slope unstable and at risk for further slides. The work qualified for federal emergency funding: the FHWA Emergency Relief Program covered 100 percent of initial cleanup and 90 percent of permanent repairs, with ODOT covering remaining costs.
For permanent repairs, crews replaced about 700 feet of rock fence and installed a new 42-inch barrier with continuous rockfall screening mounted on top to catch falling rocks. New rockfall fencing and guardrails were added at both ends of the barrier. The new system provides stronger, long-lasting protection against future rockfall, ODOT said.
A contractor also cleaned and repaired 27 culverts between Minam and Joseph. These structures channel water under the highway and protect it from flooding and erosion. The culverts had been identified in inspections as being in poor or critical condition. Work began Aug. 3 and was extended through late October when crews discovered several culverts were more damaged than expected and required replacement. The nearly $1 million project was funded through the Major Culvert Maintenance program.
ODOT will monitor the sites through winter to ensure continued safety, the agency said.